Overview
Project Owner
City of Lakeport
Value
$524,755.53
Location
Lakeport, CA
Completion
May 2017
Description
- Installation of 790LF of 18" HDPE 790 LF of 12" welded PVC sewer main
- Horizontal boring
- Connection to existing sewer
- During the intertie- required to bypass pump 600GPM of raw sewage to prevent backup
- Worked within a 4 hour time frame to complete intertie- completed in 1.5 hrs.